Planned preventative maintenance

A Decade of Spend Planned for a Listed Building

A comprehensive condition survey and ten year maintenance projection for a Grade II listed building in a London conservation area, giving the freeholder a costed plan and a tender ready schedule of works.
Copper dome and lantern of a Grade II listed tower in Islington, photographed by drone
Location
London conservation area
Building
Grade II listed, early twentieth century
Uses
Commercial units, upper parts, common fabric
Plan
About £390,000 over ten years

The property

A Grade II listed heritage asset in a designated London conservation area: an early twentieth century building comprising commercial units, upper parts and common fabric.

The brief

The freeholder needed to understand the true condition of a complex listed building, plan the spend across a decade, and structure the works so that each part of the building, its principal architectural elements, the individual commercial unit and the common fabric, could be tendered, consulted on and recovered correctly. The heritage significance of the building meant that consent requirements had to be identified before any works were programmed.

What we did

The work ran in five steps, from inspection to a schedule ready for tender.

  1. Two-stage inspectionIncluding drone photography of the roofscape and upper elements where safe physical access did not exist.
  2. Part by part gradingFindings assessed and graded for each part of the building.
  3. Ten year projectionEach item costed and placed in the year it is needed.
  4. Consents identifiedWorks to principal elements flagged for Listed Building Consent, their heritage significance tabulated so future applications start from an agreed base.
  5. Tenderable partsA schedule of works split so each part is procured separately, with its own consultation and recovery route mapped for budgeting.

The RICS standard

Planned maintenance plans are governed by the RICS professional standard Planned preventative maintenance of commercial and residential property, which sets out how the inspection is carried out and how the costed PPM schedule is reported, so the plan can be relied on for service charge and reserve fund budgeting.

The outcome

The freeholder moved from an unquantified listed building liability to a graded, costed and phased plan.

A costed ten year planAround £390,000 over ten years, front loaded where the priorities and the access economics demanded it.
Consents known in advanceListed Building Consent requirements identified before any works are programmed.
Ready to tenderA schedule of works ready to go to tender part by part.

Services demonstrated

PPM reportsBuilding surveysDrone surveyCostingTender structuring

Responsible for a listed or complex building?

We turn an unquantified liability into a costed, phased plan.