Structural Repairs Kept Under Control on an Occupied Period House

Structural repairs to an occupied period house: a competitive tender properly analysed, then a discovery led contract kept under control, with every variation valued, documented and approved before the cost was incurred.
Brick elevation and rainwater pipe on a period house during structural repairs
Property
Occupied period house, north west London
Contract sum
Around £33,000
Final account
Around £51,000, no dispute
Roles
Contract Administrator, Principal Designer

The property

A period house in north west London requiring internal and external structural repairs and redecoration, occupied by a private owner throughout.

The brief

The owner needed the repairs properly specified, competitively priced and professionally supervised, with the confidence that whatever the works uncovered would be dealt with transparently and paid for at fair rates. Avalon was appointed as Contract Administrator and Principal Designer under CDM 2015, and instructed to prepare a specification of works for tender.

Tender and selection

  1. TenderedThe specification issued to four contractors; three priced returns came back.
  2. NormalisedEach return arithmetically checked and normalised to a common basis with a full crosscast, item against item.
  3. WeighedPrice, qualification, accuracy, lead time and duration weighed together; the lowest return was also unqualified and error free.
  4. Appointed safelyRecommended subject to the CDM 2015 requirements, including a construction phase plan and method statements, before appointment.

The RICS guidance

Contract administration is covered by the RICS Black Book, including Valuing change, which is how each change the opened-up fabric revealed was priced and approved before it was carried out, with the works let on a JCT standard form.

The owner went to contract at around £33,000 knowing exactly what was and was not included.

Administering the works

Structural repair is discovery led: opening up the fabric reveals the true condition, and the scope moves. That is precisely when a contract administrator earns their fee. As the works progressed, additional repairs were instructed where the opened structure required them, and each variation was valued at contract rates, documented and reported, so the owner approved every change in cost before it happened. Seven interim valuations were issued and certified across the contract.

The owner approved every change in cost before it happened, rather than discovering it at the end.

The outcome

The owner received a structurally repaired, redecorated property and a complete paper trail: specification, tender analysis, contract, valuations, variation record and final account.

Final account around £51,000Every pound of movement traceable to an instructed, documented variation.
No disputeNothing withheld at closure.
Seven valuationsIssued and certified across the contract.

Read more about our Major Works, Managed service, available as contract administration on its own.

Services demonstrated

Contract administrationSpecification and tenderPrincipal DesignerFinal account

Repairs that could uncover more?

We keep the contract under control, with every change in cost approved before it happens.